Are You Firm With Change Request
Background: Selina (Customer Project Manager) requested to have the Implementation project schedule to move back from February to June, so as to make way for another higher prioritized project āVā. I (Service Provider Project Manager) raised a Project Change Request (PCR) to document the project is now put on hold. Project scope remains the same, is to implement the project, no change when project resume. Project schedule is moved from Feb to June. The project team will resume the…